DEVELOPMENT PHASES FOR KCOI YARD IN AKSHUKUR

KCOI yard at Akshukur site will be developed by two main subsequent investments phases simply called Phase 1 and Phase 2.
The overall time schedule for the completion of these Phases will depend also on the company success in securing contracts and producing revenues that will contribute to the financial efforts of KCOI's Shareholders.

Of course, the real market trends in next years may be rather different from what envisaged by KCOI depending on several main factors such as number and extent of projects which may (or may not) be developed by Customers in the time frames known by KCOI at the date of its original Business Plan as well as the possible different competitive scenarios due to other forthcoming Contractors investing in new fabrication facilities in Kazakhstan.

If any of these events materialize or any underlying assumptions vary in respect of what envisaged in KCOI Business Plan, then the actual plans for KCOI yard development may be affected. 

 

 

Time schedule for KCOI yard development (Phase 1)

KCOI company established

July 2008

Purchase of land plot  

December 2008

Start-up of engineering for yard development

January 2009

Start-up of yard construction works

July  2009

 Yard ready to be operational 

March 2011

YARD MAIN AREAS

The following data refer to KCOI yard full development.

Description

Values

Total length of yard sea front

~ 600 m

Total length of the quay 

~ 120 m

Quay level above average sea level 

~ 2 m

Quay strength (load per linear meter on quay edge) 

15 metric tons / linear meter

Allowable pressure in quay area 

20 Kg /cm2

Water depth in front of the quay 

Dredged to ~ 4.5 m

Width of access channel (dredged on sea bed) 

~ 200 m

Length of access channel (dredged on sea bed) 

~ 300 m

Description

 Areas (m2)

TOTAL area of KCOI land plot 

~ 485.000

TOTAL area to be developed for yard operations 

~ 185.000

Open areas for erection 

~ 61.000

Outdoors storage area 

~ 4.800

Main Covered areas:

- Structural steel fabrication and assembly workshop 

3.300

- Piping fabrication workshop 

2.200

- Sandblasting and painting workshops

1.500

- Warehouses 

770

- Maintenance workshop

320

- Offices

1.100

- Canteen + Kitchen

2.100

- Miscellaneous Utilities  

1.950

- First aid / infirmary / Gate security

280

TOTAL covered areas 

~13.500

During Phase 1 the yard will be able to build and load-out modules up to 5000 metric tons each. Then, in Phase 2 the yard will become adequate to build and load-out modules in the range of about 12.000-14.000 metric tons each.