Project Award or Delivery

EPC 4 Topside contract award

6/12/2017 0:00

On 08 June 2017, NCOC N.V. awarded to KCOI LLP - JSC Company ​MSS Joint Venture Consortium​ a new contract for the Procurement, Fabrication, Load-Out and Transportation of Topside for EP Cluster 4​ within the Kashagan Experimental Projectwith execution of works in "Temir At" yard.

Briefly the Scope of Work consists of: 

  • Endorsement of Detail Engineering Package;
  • Procurement of project materials, Shop Drawings, Method Statements;
  • Fabrication/Construction works by KCOI;
  • Electrical/Instrumentation/Telecom Installation works by consortium partner – MSS;
  • Load – Out Procedures and Load – Out Operation by skidding of 1500 ton module on barge to be transported offshore.