Scope of Work

Early Works, Site Preparation, Load-In, Installation, Hook-Up, Mechanical Completion,  Pre-Commissioning of  Topsides for EP Cluster 3 (Offshore)

Project Description

  • ​​​​​​​​​​Marine Civil Works (Early Works and Site Preparation) are done by ENKA;
  • Electrical and Instrumentation Works are done by JSC Montazhspetsstroy;
  • Load-In and Onsite Installation of Topside Modules on EPC-3 Island (Load-In Engineering, Method of Statement, On-Site Supervision);
  • Mechanical Hook-Up and Completion of Topside Facilities;
  • Pre-Commissioning and Commissioning Activities.

Technical Details

Comp​leted 2 months ahead of schedule.