Pig Traps Modification Works offshore and onshore

Status: Completed

Scope of Work

Pig Traps modification works within the Kashagan Experimental Project, with execution of works in Temir-At Yard, D-Island and Karabatan field.

Project Description

  • ​​​​Project Management - Atyrau Branch and Temir-At Yard
  • FEED Endorsement and Detail Design of the Modifications - Milan, Italy
  • Procurement of permanent material - Temir-At Yard
  • Mobilisation and Demobilisation to Island D and Karabatan
  • Removal works for existing Pig Traps in summer/autumn 2015
  • Fabrication of new cladded piping spools in early 2016 - Temit-At Yard
  • Installation and erection works on Island D and Karabatan
  • Mechanical Completion, Pre-Commissioning and Commissioning - Leak Test and Loop Diagrams
  • Handover of the Pig Traps Pacakges to NCOC N.V. for the Oil Production Start-up of Kashagan Phase 1

Technical Details

​On 31 August 2016, 40 days ahead of our scheduled date, we have handed over the Pig Traps project to our client NCOC N.V. (North Caspian Operating Company), in respect of all Safety standards and with no accidents.