Last In First Out

Publication Date
Number of views 130
Last In First Out

Last In First Out The supplementary Remote Instrument Enclosure (RIE) for Tengizchevroil FGP-WPMP plant manifold 4 (PM4), is being executed by KCOI LLP as fast track project high priority project. Awarded early summer 2019 as an integration to the existing contract for no. 9 RoK built RIE, it is currently under the final stages of outfitting. Conclusion of mechanical completion activities is imminent and proceeding on time towards handover for commissioning by mid-December, on corse for final delivery end January 2020, as scheduled. Project manager Anthony Iveson stays optimistic and very satisfied with the extraordinary efforts made and results obtained by the integrated project team: "Once again, the commitment and focus of the Project team remains strong, all yard personnel and subcontractors are working diligently to achieve success in a safe working environment to another challenging schedule"